Ref: JT 11- 580006                 January 14, 2015            

To:                  The President
    The Stock Exchange of Thailand
Re:    Progress of the construction of uncompleted project

As TRUE Telecommunications Growth Infrastructure Fund ("the Fund") has invested 
in the uncompleted telecommunications infrastructure assets on December 25,
2013, SCB Asset Management Co., Ltd. ("the Company''), the Management Company of
TRUE Telecommunications Growth Infrastructure Fund, would like to inform the
progress of the uncompleted project pursuant to the letter of the Office of the
Securities and Exchange Commission No. Thor Nor. 1/2554 with details as follows:
Under the Asset and Revenue Sale and Transfer Agreements between True 
Corporation Public Co., Ltd. ("True") and the Fund dated December 24, 2013, True
will be obligated to deliver or procure the delivery of the new towers of 3,000
towers due for delivery by December 31, 2014 ("First Batch") and the remaining
3,000 towers due for delivery by December 31, 2015 ("Second Batch") (both
related to as "Additional Telecommunications Towers"). At the end of December
2014, the Actual Progress of the Construction of the Additional
Telecommunications Towers compared to the Plan and the Delivery of the
Additional Telecommunications Towers are summarized as follows:    
Table 1 Summary of the Actual Progress of the Construction of the Additional 
Telecommunications Towers (Number of sites) compared to the Plan at the end of
December 2014
Key Milestones
Plan
end of December 2014
Actual Progress
end of December 2014

Site Option Approved
Technical Site Survey
Negotiation, Site Rental Approval
Site Lease Contract Signed
Submission of request for the Approval and License from the Government Agency
Start of the Construction
Inspection and Delivery of the towers to the Fund
4,720
4,540
4,380
4,020

3,840
3,200
3,000
4,901
4,667
4,505
4,137

3,961
3,323
3,021











Table 2 Report on the Delivery of the First Batch of Towers to the Fund for the 
period of June - December 2014
Month    June
July
August
September
October
November
December

Monthly Plan of the First Batch Delivery (Year 2014)

Delivery Amount
-    68    540    600    750    600    390
Total Accumulated Amount    -    120    660    1,260    2,010    2,610    3,000
Monthly Actual Delivery Amount (Year 2014)

Actual Delivery Amount
52    77    261    643    267    717    1,004
Total Accumulated Amount
52    129    390    1,033    1,300    2,017    3,021
From the reports above, the construction progress of the Additional 
Telecommunications Towers is in accordance with the Plan and there have been no
event indicating that the delivery of the Additional Telecommunications Towers
will not be on the schedule.


Please be informed accordingly.

Yours faithfully,
TRUE Telecommunications Growth Infrastructure Fund
By SCB Asset Management Company Limited




(Mr. Sarnthor Mudhasakul)
Vice President, Property and Infrastructure Fund Group
______________________________________________________________________
This announcement was prepared and disseminated by listed company or issuer 
through the electronic system which is provided for the purpose of dissemination
of the information and related documents of listed company or issuer to the
Stock Exchange of Thailand only.  The Stock Exchange of Thailand has   no
responsibility for the correctness and completeness of any statements, figures,
reports or opinions contained in this announcement, and has no liability for any
losses and damages in any cases.  In case you have any inquiries or
clarification regarding this announcement, please directly contact listed
company or issuer who made this announcement.